Kiwi Rail Project
Auckland Waterfront
The Auckland Waterfront Block of Line works conducted for Kiwi rail, comprised of 220 meters of pavement construction under time pressure restraints. The project had a 5 day working program with 24hr rotating shifts. The project had been completed 1.5 days ahead of schedule finishing up on New Years eve 2022.
Block of Line
Kāpehu specializes in high speed rail construction detailing in pavement construction, geotechnical remediation, piling and retaining along with UTX and infrastructure service installation.